Month of September 2004
Date |
Task |
Time Spent(mins) |
9/7/04 |
Project assigned, initial meeting with team to introduce ourselves and exchange contact information. |
30 |
9/14/04 |
Met with team in class to discuss some initial ideas, impressions about project |
25 |
9/14/04 |
Met with team in class, discussed webpage and time logs |
30 |
9/15/04 |
Started working on the website |
45 |
9/16/04 |
Came up with some questions for our client Dr. Weinberg |
20 |
9/16/04 |
Met with Sean and Joe in class to coordinate our test questions while Mike was in the managers meeting |
15 |
9/20/04 |
Meeting with our client, Dr. Weinberg to define project, a short team meeting afterwards to assign roles. Roles discussed and assigned |
120 |
9/21/04 |
Brainstorming session for camera control feature, came up with a team name |
25 |
9/24/04 |
Met with team in class, discussed a conflict resolution plan, and ethical considerations |
25 |
9/9/04 |
Met with team in class, discussed website, time logs, and documentation goals |
75 |
9/23/04 |
Meeting with our client, Mr. Lamonica to discuss the technical aspects of our project |
75 |
9/23/04 |
Worked on the website |
180 |
9/24/04 |
Contd. working on the website |
180 |
09/26/04 |
Contd working on the website |
90 |
09/28/04 |
Meet with team in class and discussed about the group presentation |
30 |
09/30/04 |
Meet with team in class and discussed about the presentation. Also sent e-mail to Andrew Lamonica to get access to Marvin.
|
30 |
|
Total |
16.58hrs |
Month Of October 2004
Date |
Task |
Time Spent(mins) |
10/03/04 |
Worked some more on the website. |
240 |
10/04/04 |
Worked on the design of the interface with Mike. |
180 |
10/05/04 |
Met with team in class to discuss some more details about the screen mockups. |
25 |
10/05/04 |
Met with team to discuss about the new team member. Also discussed about the initial presentation |
90 |
10/06/04 |
Met with Mike and contd to work on the interface design |
180 |
10/07/04 |
Met the new team member and introduced each other |
20 |
10/07/04 |
Met with team to discuss more about the forthcoming presentation |
75 |
10/09/04 |
Worked on the website to make some changes. |
120 |
10/10/04 |
Met with team to discuss more about the forthcoming presentation |
75 |
10/11/04 |
Worked on the website to make some changes. |
120 |
10/12/04 |
Worked on the presentation with Mike |
90 |
10/13/04 |
Presented intial design ideas to the Client |
30 |
10/13/04 |
Contd to work on the presentation |
150 |
10/14/04 |
Contd to work on the presentation with Mike. Final assembly of the presentation slides. Presented the Project Defination Presentation. |
120 |
10/19/04 |
Updated the logs on the website. |
30 |
10/19/04 |
Team meeting in class, discussed our next step in the project. Discussed about the Design Presentation which is due in the first week of November. |
60 |
10/25/04 |
Worked on the website. Updated title of the website and also made some changes to the team members. |
60 |
10/26/04 |
Researched on how to develop java applets. |
90 |
10/27/04 |
Researched some more on java classes and how to include it in html |
120 |
10/28/04 |
Met with the team in class, while the project manager was away on a manger's meeting. Topics discussed was about the forthcoming prject defination presentaion. |
40 |
10/28/04 |
Met with the team outside class and discussed about the web interface and the contents of the forthcoming presentation. |
90 |
10/30/04 |
Updated the website. Main page contents were updated. |
60 |
10/31/04 |
Updated the website. Updated the log files. |
60 |
|
|
|
|
Total |
35.41hrs |
Month Of November 2004
Date |
Task |
Time Spent(mins) |
11/02/04 |
Worked on the design presentation |
180 |
10/03/04 |
Worked on the design presentation |
180 |
11/05/04 |
Met with team in class to discuss some more details about the screen mockups. |
25 |
11/06/04 | Went over the existing java classes for the robot. | 90 |
11//08/04 | Worked on the presentation slides | 120 |
11/09/04 |
Updated the team logs. |
30 |
11/10/04 |
Discussed with the team about the Project Plan presentation |
25 |
11/11/04 |
Met with the team and discussed the documentation requirements. Also went over the project plan presentation notes, and discussed thematerial. |
120 |
11/12/04 |
Worked on the website. Updated my log |
30 |
11/13/04 |
Worked on the Customer Contract document and the coding standards document. |
120 |
11/14/04 |
Updated the website and some of the log files. |
30 |
11/16/04 |
Met with Andrew Lamonica to learn more about the existing middleman server and how the applet interacts with the middleman. Also learnt more abou the different classes and how to test it in Eclipse which is an IDE for Java |
120 |
11/16/04 |
l Updated my log files and also the client meeting notes. |
20 |
11/17/04 |
Met With Dr.Fujinoki to discuss the possibilities of Audio streaming via multicasting. Outcome was the idea of using MBONE. |
40 |
11/18/04 |
Team meeting. Discussed the forthcoming presentation. Also decided to meet during the break and work on the system design and project plan presentation. |
90 |
11/20/04 |
Researched how to create applets in java for the camera controls and the screen. |
90 |
11/21/04 |
Downloaded the current robotics webpage and worked on building an applet for the final presentation. Slow progress |
120 |
11/22/04 |
Spent some time on vedio streaming, and coming up with a time line for the development camera controls. |
120 |
11/23/04 |
Learnt Java |
30 |
11/24/04 |
Learnt Java |
30 |
11/25/04 |
Learnt Java |
30 |
11/26/04 |
Learnt Java |
30 |
11/27/04 |
Learnt Java |
30 |
11/29/04 |
Got together with Mike and discussed the timeline and the schedule. Also gave some thought to the Project Plan presentation. |
60 |
11/30/04 |
Worked with Mike on the presentation material. |
180 |
|
Total |
34.29hrs |
Month Of December 2004
Date |
Task |
Time Spent(mins) |
12/01/04 |
Worked on the design presentation |
120 |
12/02/04 |
Worked on the design presentation with Mike and came up with a detailed time line for the forthcoming semester |
120 |
12/05/04 |
Met with Mike and worked on the web applet interface. Also looked at using java awt and java swing implementations for the applet. Decided to go with the java awt implementation for the final demonstration. |
600 |
12/06/04 |
Researched java awt applet implementation. Laying out controls seems to be a big problem, so was looking at swing implementation. |
60 |
12/07/04 |
Met with the team and discussed the final presentation |
90 |
12/07/04 |
Worked on the java applet prototype |
180 |
12/08/04 |
Met with Joe and worked on the integration of the map with the camera contorl applet |
90 |
12/08/04 |
Met Andrew Lamonica to talk about the procedure for starting up Taz. |
90 |
12/08/04 |
Worked on the Java applet protype, integrated the map and implemented the controls. |
360 |
12/11/04 |
Made changes to the website. Also the applet is almost ready, worked on the applet some more to incorporate all the features. |
90 |
|
Total |
29.5hrs |