Matt Stowe

Day

Time

Type

Description

WEEK 1

 

 

 

Thursday

Jan 12, 2006

 

1.25 hours

Group meeting

The group discussed the flow of the interface and the function call to be made between systems.

Friday

Jan 13, 2006

 

2 hours

Programming

Added additional functionality to interface code( added player 3 and 4)

WEEK 2

 

 

 

Tuesday

Jan 17, 2006

1.25 hours

Group meeting

Continued function definition from previous meeting

Wednesday

Jan 18, 2006

4 hours

Group Programming

Aaron and I worked on the interface code to organize and simplify existing code and adding functional comments

Thursday

Jan 19, 2006

1.25 hours

Group meeting

Continued function definition from previous meeting and discussed legal ramification of our program with upper management

WEEK 3

 

 

 

Monday

Jan 23, 2005

3 hours

Programming

Continued programming from last Wednesday

Tuesday

Jan 24, 2006

1.25 hours

Project Presentation

Presented Status Report

Friday

Jan 27, 2006

6 hours

Programming

Changed to programming four players into the prototype

WEEK 4

 

 

 

Tuesday

Jan 31, 2006

1.25 hours

Group meeting

Worked on the time line a GANTT chart.

Thursday

Feb 02, 2006

0 hours

Group meeting

Meeting canceled due to faculty presentation

Thursday

Feb 02, 2006

4 hours

Programming

Completed four player prototype programming

Friday

Feb 03, 2006

6 hours

Testing

Massive debugging on four player prototype code

WEEK 5

 

 

 

Tuesday

Feb 07, 2006

1.25 hours

Group meeting

Discussed the HCI issues and Todd’s very updated interface design

Thursday

Feb 09, 2006

1.25 hours

Group meeting

Final Revision for timeline for next presentation, and further discussion of the phase one project

Thursday

Feb 09, 2006

4 hours

Programming

Started coding the last parts of phase one save game and logs.

WEEK 6

 

 

 

Tuesday

Feb 14, 2006

6 hours

Programming

Finished coding the save game and fixed a great many HCI bugs and other errors

Wednesday

Feb 15, 2006

2 hours

Group meeting

Discussed my changes to the game and the presentations for Thursday

Wednesday

Feb 15, 2006

6 hours

Programming

Finished coding logs and finished updating the interface for optimal use. Also added movable token rather than colors

Thursday

Feb 16, 2006

1.25 hours

Project Presentation

Presented Status Report

WEEK 7

 

 

 

Tuesday

Feb 21, 2006

1.25 hours

Group meeting

Started discussing AIs

Thursday

Feb 23, 2006

1.25 hours

Group meeting

Continued AIs

WEEK 8

 

 

 

Tuesday

Feb 28, 2006

1.25 hours

Group meeting

Continued AIs

Thursday

Mar 02, 2006

1.25 hours

Group meeting

Continued AIs

WEEK 10

 

 

 

Tuesday

Mar 14, 2006

1.25 hours

Group meeting

Continued AIs

Thursday

Mar 16, 2006

1.25 hours

Group meeting

Prepared for Status Report

WEEK 11

 

 

 

Tuesday

Mar 21, 2006

1.25 hours

Project Presentation

Presented project (discovered that our AI would not work)

Thursday

Mar 23, 2006

1.25 hours

thinking

Come up with scripted AIs

WEEK 12

 

 

 

Monday

Mar 27, 2006

3 hours

programming

Wrote first part of AI in C++

Tuesday

Mar 28, 2006

1.25 hours

Group meeting

Continued work on AIs

(come up with scripts)

Wednesday

Mar 29, 2006

2 hours

programming

Continued  AI in C++

WEEK 13

 

 

 

Wednesday

Apr 05, 2006

6 hours

Programming

Finished first AI in c++

Second ½ done

Thursday

Apr 6, 2006

1.25 hours

Group meeting

discussed Status Report

WEEK 14

 

 

 

Tuesday

Apr 11, 2006

1.25 hours

Project Presentation

Presented Status Report

Wednesday

Feb 12, 2006

2 hours

Programming

Finished second AI in c++

Saturday

Apr 15, 2006

1.25

hours

testing

I found out that c++ sockets and VB socket do not comunicate

WEEK 15

 

 

 

Tuesday

Apr 18, 2006

1.25

hours

Group meeting

Discussed the socket problem

Wednesday

Apr 19, 2006

4 hours

programming

Fixed/created Ai header in VB

Thursday

Feb 16, 2006

1.25 hours

Group meeting

Dicsussed AI writing in VB

Saturday

Apr 22, 2006

5 hours

programming

Finished AI header in vb and started on the AIs in VB

Sunday

Apr 23, 2006

4 hours

programming

Finished AI template in VB

WEEK 16

 

 

 

Monday

Apr 24, 2006

10 hours

Programming

Wrote AI 1 2 and 3

Monday

Apr 24, 2006

4 hours

testing

Tested all three AIs and debugged them

Tuesday

Apr 25, 2006

1.25 hours

Group meeting

Discussed Final Presentation

Wednesday

Apr 26, 2006

3 hours

Programming

Fixed all three AIs to allow for saved games

Thursday

Apr 27, 2006

1.25 hours

Group meeting

Discussed Final Presentation

Friday

Apr 28, 2006

2 hours

Practice presentation

Gave a practice presentation

Sunday

Apr 30, 2006

3 hours

Programming

Fixed error in AI saved games